The Aidarov family
2/10/2026
7/15/2026
7
Timeline
- Day 1557/15/2026
Handover
Handed over on the contract date, to the day. The 47-point inspection is signed off and the family has the building passport, the first-firing protocol and a twelve-month maintenance schedule.


- Day 1246/14/2026
Roof, glazing, stove
Envelope closed: roof, glazing, entrance group. The enclosed-stone stove is set, the flue is run, and the first-firing protocol is under way.

- Day 965/17/2026
Raising the shell on site
The shell went up on the foundation in 11 shifts. Every course seated on its dowels without refitting — the workshop marking matched log for log.

- Day 784/29/2026
Delivery to Almaty
A 3-truck convoy cleared the border. Unloading on-site tomorrow.

- Day 473/29/2026
Hand-hewing the log shell
At our workshop, master carpenters are hand-hewing the first-floor logs. 12 days until shipment.

- Day 142/24/2026
Cedar harvest in Kuragino
Our Krasnoyarsk team harvested the cedar. First batch is heading for drying.

- Day 12/10/2026
Day 1 · Site survey
Architect visited the Almaty site, took measurements, agreed on banya placement. Contract signed.