GLOBALKRAFTCentral Asia
The Aidarov family · Almaty
Almaty · Siberia · Delivered

The Aidarov family

ResultDelivered in 155 days
100%
Start

2/10/2026

Handed over

7/15/2026

Updates

7

Timeline

  1. Day 1557/15/2026

    Handover

    Handed over on the contract date, to the day. The 47-point inspection is signed off and the family has the building passport, the first-firing protocol and a twelve-month maintenance schedule.

    Handover
    Handover

  2. Day 1246/14/2026

    Roof, glazing, stove

    Envelope closed: roof, glazing, entrance group. The enclosed-stone stove is set, the flue is run, and the first-firing protocol is under way.

    Roof, glazing, stove

  3. Day 965/17/2026

    Raising the shell on site

    The shell went up on the foundation in 11 shifts. Every course seated on its dowels without refitting — the workshop marking matched log for log.

    Raising the shell on site

  4. Day 784/29/2026

    Delivery to Almaty

    A 3-truck convoy cleared the border. Unloading on-site tomorrow.

    Delivery to Almaty

  5. Day 473/29/2026

    Hand-hewing the log shell

    At our workshop, master carpenters are hand-hewing the first-floor logs. 12 days until shipment.

    Hand-hewing the log shell

  6. Day 142/24/2026

    Cedar harvest in Kuragino

    Our Krasnoyarsk team harvested the cedar. First batch is heading for drying.

    Cedar harvest in Kuragino

  7. Day 12/10/2026

    Day 1 · Site survey

    Architect visited the Almaty site, took measurements, agreed on banya placement. Contract signed.

    Day 1 · Site survey
The Aidarov family · build in real time · Global Kraft